• Tech Tech

Local opposition tied to 75% of 146 delayed or canceled US data center projects, S&P says

A moratorium can give utilities, planners, and elected officials time to decide whether a project fits an area before construction locks in lasting impacts.

People protesting data centers.

Photo Credit: Getty Images

Local resistance is having a major impact on the United States data center rush. S&P Global Ratings said pushback could affect project credit quality as disputes over noise, water use, and power demand delay or halt development.

Here's what to know

S&P Global Ratings tracked 146 projects that were delayed or canceled. Roughly 3 in 4 were linked to local pushback, a sign that residents and officials hold influence as the fast-growing infrastructure gets built.

Analysts, including S&P Global Ratings analyst Chris Mooney, examined pause orders in New York, Texas, Pennsylvania, Illinois, and Arizona, according to Insurance Journal, which cited an S&P Global Ratings report.

S&P said that moratoriums, zoning revisions, and environmental objections can spill over into project financing, making disputes over noise, water use, and power demand relevant to credit quality.

Its conclusion was that delays linked to grid capacity constraints, environmental sustainability concerns, and zoning shifts "could increase downward pressure on the creditworthiness of data center projects," per Insurance Journal.

Among the complaints raised most often are higher power costs, limited water supplies, air-quality concerns, and noise. Those issues are especially concerning for creditors, as they can show up in family budgets, strain local resources, and change everyday living conditions, meaning they are rooted in physical reality rather than simply perspective.

A moratorium can give utilities, planners, and elected officials time to decide whether a project fits an area before construction locks in lasting impacts.

More background

Public scrutiny of the industry has deepened enough that local governments in 40 states have imposed bans.

Those bans point to a pattern in which communities have tried to slow, limit, or reshape development that could add pressure to local systems or cause quality of life issues.

S&P said credit grades have been only limitedly affected, even as the firm seemingly tied neighborhood-level resistance to the broader credit risks of large-scale development.

Problems become more serious for the creditors when a holdup affects lease terms, the firm said. A long delay or project reversal can leave developers owing rent credits and granting tenants the option to terminate agreements.

The concerns behind the opposition — from grid capacity and clean air to water supply and persistent noise — are a bigger worry for nearby residents than a potential credit issue for a developer.

What's being done?

Bans have been imposed across most of the U.S. as officials respond to resident concerns and reconsider where data centers should be allowed.

Communities are also responding through permitting slowdowns and zoning changes. Those steps can buy time to assess whether local power systems can support new projects and whether environmental impacts have been properly addressed.

S&P also emphasized a trade-off. Projects that depend on opening on schedule can face financial strain when approvals stall. Even if construction eventually moves ahead, that can still weigh on a developer's credit profile.

S&P said that the financial fallout remains limited, but it added that "to the extent that moratoriums, permitting slowdowns, or potential reversals meaningfully delay projects, financial penalties in the form of rent credits and even tenant termination rights pose credit risk."

Where can I learn more?

These articles look at how local resistance, moratoriums, and concerns about water and power are affecting data center expansion across the U.S.

• In North Carolina, three localities weigh moratoriums as one capital plan gets pulled.

• In Pennsylvania, residents appeal second data center approval despite doubts about board authority.

• In Texas, AI expansion backlash halts 1,800 projects and spills into politics.

Get TCD's free newsletters for easy tips, smart advice, and a chance to earn $5,000 toward home upgrades. To see more stories like this one, change your Google preferences here.

Cool Divider