Florida crews must pump out 62 manholes to fix aging grid after repeated downtown outages

"The heat is an indicator that that piece of equipment is starting to fail."

Lakeland, Florida.

Photo Credit: iStock

Restoring downtown Lakeland's aging electric grid comes with the unusual challenge of pumping water out of 62 manholes before crews can reach the equipment below.

Florida utility workers must remove hundreds — sometimes thousands — of gallons as they work to prevent further outages that disrupt local businesses, the utility said.

Here's what to know

Finding trouble spots and replacing equipment before it fails are the goals of Lakeland Electric's Downtown Reliability Project, LkldNow reported. Downtown Lakeland businesses experienced at least three power interruptions in 2026 on Feb. 20, July 17, and Oct. 20.

The utility said downtown reliability exceeded the national top-quartile benchmark during 2020–2025, meaning customers had less frequent or shorter service disruptions, or both, than customers of most U.S. utilities. Performance began slipping in 2025, however.

Much of downtown's development dates to the 1990s, according to Lakeland Electric. The utility therefore has both old and new infrastructure to maintain.

Scott Bishop, Lakeland Electric's interim general manager, outlined the expected replacement timeline.

"We've got to make sure that our infrastructure is being replaced on a 35 or 40 year amortization," he said. "Transformers are 35 to 40. Some conductors should be good for 50."

More background

Some manholes are 12–14 feet deep, according to lead transmission/distribution lineperson Travis Mcpherson, LkldNow reported. Entering those spaces requires confined-space training; crews may also need help from Public Works Department staff to remove the water.

Businesses operating throughout the week complicate downtown repair schedules. Bishop said repairs can also involve permits, overnight work, and sidewalk or road closures.

"It is difficult when you are trying to run a downtown and also fix infrastructure," Julie Townsend, who heads the Lakeland Downtown Development Authority, told LkldNow.

An equipment replacement at the end of October was followed by another outage when power returned, and a different spot failed. Crews had rerouted customers' electricity to replace the failing equipment, but the subsequent failure required further repairs.

What's being done?

The project's first phase, completed in 2025 at a cost of about $200,000, included a grid survey and inspections of every above-ground transformer, LkldNow reported.

A multiyear repair plan was another product of that work. Crews also installed or repaired fault indicators to help lineworkers locate equipment problems.

Workers use infrared cameras to identify unusually hot equipment, with inspections covering 32 switch compartments and 32 transformers. The second phase, estimated at $250,000, focuses on the underground system.

Matt Mills, Lakeland Electric troubleman supervisor, explained what those readings reveal.

"The heat is an indicator that that piece of equipment is starting to fail," he said, according to LkldNow. 

Cable condition and remaining lifespan will determine which cables get replaced first during the third phase, scheduled for completion in 2027. The utility estimates that work will cost $500,000.

A final phase could cost about $1 million annually for three to five years and would replace older connections, switchgear, transformers, and cables.

Downtown drew renewed attention from Lakeland Electric's reliability committee when its performance began changing, Bishop said. The committee reviews problem circuits across the utility's service territory.

"We're always chasing the reliability, always," Bishop said, according to LkldNow.