The MBTA's repair and upgrade program is expected to cause fewer construction-related disruptions for Boston transit riders.
The agency anticipates 100 days of planned service outages, down from 274 in 2024, a reduction of nearly 64%.
Here's what to know
The MBTA's 2027 construction schedule puts most subway interruptions on weekends to reduce disruption for riders, according to NBC Boston.
Signal work will include improvements in the Green Line's central tunnel and the completion of major upgrades on the Red and Orange lines.
The agency credits investments in tracks, signals, and other infrastructure with making trips faster and more dependable. Diversion days have declined over several years, with 132 in 2026 compared with 190 in 2025.
Work in the Green Line's central tunnel includes a January 16-24 suspension. Orange Line track work will interrupt service between North Station and Ruggles from May 15-23, and Blue Line service between Bowdoin and Airport will be suspended June 18-27 for track renewal.
More background
MBTA General Manager and CEO Phillip Eng said assessments in 2023 showed that 65% of the system didn't meet State of Good Repair standards, leaving a substantial maintenance backlog ahead of the construction push.
He said crews have modernized much of the signal infrastructure and replaced hundreds of thousands of feet of rail since 2024.
The Green Line's new central tunnel signals are designed to improve train detection, help operators manage congestion, and maintain more consistent spacing between trains. The equipment will also accommodate the forthcoming Type 10 Green Line cars.
October marked the first time since the pandemic that the transit agency recorded weekday ridership above 1 million, the agency reported.
What's being done?
Symphony Station will remain closed through spring 2029 while crews install four elevators and complete other upgrades intended to make the 85-year-old Green Line station fully accessible.
On the Green Line's B Branch, trains won't run from Babcock Street to Boston College for three December weekends, according to NBC Boston. Crews will work on improvements at inaccessible above-ground stations along Commonwealth Avenue, raising platforms eight inches above the rails and widening, leveling, and lighting boarding areas.
At Downtown Crossing, an October 8-11 Orange Line closure affecting stops from North Station to Back Bay will allow crews to work on two accessible transfer elevators, according to NBC Boston.
Track-tie replacement will disrupt off-peak weekday trains running from Forest Hills to Needham Heights from March into May, and between Newburyport and Ipswich from March into June.
MBTA General Manager and CEO Phillip Eng acknowledged the patience riders need as the work continues.
"In 2023, 65% of the system was found to be out of State of Good Repair (SGR)," he said. "The work we've performed since 2024 during weekend and multi-day outages is showing incredible, tangible progress for our riders – we've replaced hundreds of thousands of feet of rail, upgraded much of our signal infrastructure, and enhanced so many other areas of the system, which have provided riders with faster, more reliable trips, and given them back precious minutes in their day. The new way the MBTA does business works! And our riders are feeling our commitment to that progress every day.
"I want to personally thank the public for their patience while we deliver the robust, reliable, worldclass transit system they expect and deserve."
Get TCD's free newsletters for easy tips, smart advice, and a chance to earn $5,000 toward home upgrades. To see more stories like this one, change your Google preferences here.