The time of day could determine the price of electricity under a rate option being considered by the municipal utility in Marblehead, Massachusetts.
The rate review coincided with plans for a roughly $10 million substation rebuild and the replacement of aging meters.
Here's what to know
While the utility's existing meters can track when customers use electricity, the system cannot reliably turn those readings into bills with rates that vary throughout the day, often known as "time-of-use" rates. The utility has made replacing that system a priority for 2027, according to Marblehead Weekly News.
John Blair, the municipal utility's general manager, has discussed putting together a time-of-use proposal for review by the Municipal Light Commission, with the rate design and rollout schedule still to be determined. Time-of-use pricing could give residents a reason to move some household activities to off-peak hours, saving energy-intensive tasks like laundry or running the dishwasher for periods with lower rates.
As part of its five-year capital outlook, the utility planned to borrow money for work on the Clifton substation, according to Marblehead Weekly News. Excluding future borrowing, the account used to fund capital work could hold less than $1 million by 2030, down from roughly $5.5 million at the beginning of 2026.
Commissioners also discussed whether to use state-law provisions authorizing property liens to collect unpaid electric bills. Fewer than 10 customers would be affected, according to the department.
The measure would be an option to collect substantial, long-overdue debts from a small group of customers, including those whose electricity cannot be shut off. One proposal floated a $2,500 threshold for such extreme collection efforts, while other recommendations included minimum lengths of time that a debt must have been owed in order to qualify.
What else is being done?
Replacement transformers at the Village substation are expected to begin operating December 2, according to Marblehead Weekly News. The department has been testing the replacements while the existing equipment remains in use, and a contractor is scheduled to start draining and dismantling the old units on the switchover date.
Meanwhile, the federal Department of Energy and the Massachusetts Clean Energy Center are providing a $1.3 million grant for a separate project to strengthen Marblehead's transmission connections. The grant is expected to be paid as reimbursements, with $650,000 arriving in 2027 and the remaining $650,000 in 2028.