Residents in Greenfield, Massachusetts, face a $1.87 million annual bill after a regional project won approval.
Voters approved a new technical school building projected to cost hundreds of millions of dollars, but the question of funding remains in limbo.
Here's what to know
The $236.6 million Franklin County Technical School project passed across its 19 member municipalities by a combined vote of 4,106 to 3,522, according to the Greenfield Recorder.
Greenfield faces the largest annual assessment among the member communities, despite its voters rejecting the project 834 to 755.
Buckland, Shelburne, Colrain, and Orange also voted against it.
The Massachusetts School Building Authority plans to cover 66.27% of eligible costs, with its contribution capped at $113.8 million, meaning the municipalities will need to borrow $122.8 million.
Some site and project expenses fall outside the state's reimbursement rules.
Greenfield's City Council unanimously approved a letter to Gov. Maura Healey and the authority on Oct. 21, seeking supplemental capital support. Buckland, Conway, Deerfield, and Gill have requested help alongside Greenfield, the Recorder reported.
More background
Greenfield's letter argues that the state's reimbursement formula fails to account for vocational schools' specialized space requirements or keep pace with inflation.
Large bays and high ceilings, for example, can be classified as excessive or ineligible for reimbursement, leaving communities to cover those costs. However, the letter connects these facilities to training skilled workers for local trades and the state's green energy transition.
A Franklin Tech document shows that Buckland faces an annual capital assessment of about $219,500, while Conway's is about $238,000. Conway Selectboard Chair Christopher Waldo also pointed out the costs for work that needed to be done on the curb and parking area at Conway Grammar School.
Greenfield's letter warns that school debt could push communities to seek debt exclusions or Proposition 2½ overrides, limiting funding for other public services.
What's being done?
Deerfield, which faces an annual assessment of about $697,000, is asking lawmakers to approve additional grant funding through the state building authority. Its letter also calls for expanded vocational-school grant capacity beyond the authority's annual funding cap.
The authority's board has increased the amount it will fund per square foot to $605, up from $586. Deerfield's letter welcomes the increase but argues that the change does not address the distinct needs of vocational schools.
The letter also questions per-student reimbursement limits of $1,915 for furniture, fixtures, and equipment and $1,570 for computers. Those allowances, it argues, overlook required industrial equipment such as welding stations, vehicle lifts, and machine tools, according to the Recorder.
Meanwhile, Franklin Tech's unofficial School Committee minutes describe discussions with state Sen. Jo Comerford about continued collaboration. Members also suggested approaching the federal delegation about funding earmarks.
Greg Snedeker, Deerfield's assistant town administrator, drafted additions to the town's request. He emphasized that supporting the school and seeking financial relief are not at odds.
"Obviously, we supported it, we voted for it," Snedeker said, "but now we're in sticker shock and hoping for a little extra if we possibly can."
Where can I learn more?
Greenfield's school debt concerns are part of a wider squeeze on Massachusetts school and municipal budgets.
• In Massachusetts, Burncoat school options reach $710 million, with tax hikes or cuts possible.
• In Wayland, Massachusetts, a $56.7 million capital plan would ask voters to approve higher taxes.
• Franklin County, Massachusetts, schools lose more than 40 staff as insurance and salary expenses soar.
Get TCD's free newsletters for easy tips, smart advice, and a chance to earn $5,000 toward home upgrades. To see more stories like this one, change your Google preferences here.